PhytoMedic V1 — Delivery Timeline (13 Weeks)
1 PM1 BA2 FE3 BE1 QA · Senior-level team · No juniors
Sprint
W1
W2
W3
W4
W5
W6
W7
W8
W9
W10
W11
W12
W13
Sprint 0Env setup
Env setup · API access
Sprint 1Auth + KYC
Auth + KYC + Multi-tenant + Cannametrics schema
Sprint 2Presence + QES
Presence + Patients + Appointments + QES Signing
Sprint 3Rx + Routing
Prescriptions + Routing + Cannametrics snapshots
Sprint 4Admin + Audit
Admin + Audit + Notifications + Web
Sprint 5QA + Deploy
QA · UAT · Deploy · Docs
Cannametrics+120h parallel
Cannametrics data foundation (1 BE dev, parallel track — no critical path impact)
13 weeks total
~2,249h effort
$29,293 (v6.0)
8 devs + PM + BA + QA
Cannametrics +120h built by 1 backend dev in Sprints 1–3 as parallel track — no critical path impact.